Low Level Track Phase Five / 2009
This was to extend Phase three around to pond Junction
The lads are busy again making track panels for the 5th phase. We are taking about laying this lot first. The start of it is at the points that lead in to the carriage sheds up to around the corner to the next point by Ted's Hut.
Unfortunately there is going to be a lot of major works around this area with 5 new points a X over (Diamond Crossing) all to be made and installed.
The set of points are well under construction which fit and join on to the phase three and carriage sidings. There lots of panels made in the corner.
Works Started 11 Jan 2009
Feb 2009
We had an opportunity to take this section of track out of service and replace it with the made up panels. A new point had to be made and fitted into the line for the carriage shed branh. Then fit the new sections of track back to teds hut.
We went back to Phase Four Part 2 for the rest of 2009 after this small section had been completed.
At the end of Jan 2010 we started phase Six. Pond Junction